Loan Day: 101
The framers came back today and finished up the "Honey-Do" list that we had...
The OSB board on top of the tub deck...
The entry door from the garage to the laundry room. Now we can have the house locked up.
Basement stairs are done. These stairs will be open to the great room area, to make it part of the house. But until the downstairs is finished, then there will be a door at the bottom of the stairs.
More duct work from the furnace is done. They said they are about 80% done with their work.
First sight of seeing someone use the electricity in the house! There is one outlet so far, just this one.
The issue of the fireplace venting is fixed and the truss is ready for the fireplace people to come back out and finish the venting.
Garage floor is cured and looks great!
Roofers finished the top ridge vent and also finished up these plumbing waste flashings that my plumber couldn't get to.
The rest of the shingles are brought down to the roof level so now Tony's brother Dan can get to them when they pick them up for returning to Chelsea Lumber for credit.
Here is the end of our driveway, where it meets the road. Im actually standing at the area where the road meets the driveway.
Locked up and ready for key access only!