Loan Day: 100
Lots going on today.. Consumers came out yesterday and rolled out the electric line and then today they dug in the ground and buried the gas and electric all the way to the house.
We also saw that Cooks came out and poured the garage and driveway apron, which was totally unexpected! Well now we wont have to bother them in getting that done.
The framers worked on a few things from my list.. setting up the master tub deck for the drop in tub...
Getting the pieces ready for the basement stairs.
Pocket door frame is set in my master closet.
Pocket door frame is also set up in the entryway between the kitchen and the laundry room.
More pieces getting ready for the basement steps.
Finished products from Consumers. We have an electric meter and the gas meter hooked up.
Basement doors are in now too. Im looking forward to the sunlight and entry down here.
Furnace has been started to be installed.
Another view of the house now with the garage apron. We plan to do gravel stone for the rest of the driveway for now. Its just too expensive for concrete the whole length, for as long as the driveway is.